POWER MECH PROJECTS LTD
BALCO 4 X 300MW, EXPANSION PROJECT FOR CUTTING OF C.T.RISER PIPE’S HOOK UNIT# 1 & 3 & 4
PURPOSE:
- Methodology of cutting of temporary hook.
SCOPE:
- This procedure will
cover the requirements of cutting of temporary riser pipe hook
TECHNICAL
CONFIGURATION: - Presently temporary supports cutting work is to be
performed. So for cutting the hook support, we will adopt the following
procedure.
MAJOR PLANT & M/C
DEPLOYED:-
Capacity/SWL Quantity
1.
Gas Cutting Set
: 01 Nos.
2.
Oxygen Cylinder : 01 Nos.
3.
LPG Cylinder
: 01 Nos.
PROCEDURE:
-
1. According the situation of the
temporary hook support, the rope ladder and necessary fall arrester will be
prepared with proper approach and its required PPEs and 25 mm life line will be
provided for anchoring the safety harness.
2. During cutting work the affected area
will be barricaded. The gas cylinders will be kept away about 5mt distance and
the LPG cylinder will be covered with proper sheeting.
3. If required the fall arrestor will
also be provided.
4. Before cutting the scrap it will be
anchored with the rope to avoid falling down and after cutting, it will be
shifted at scrap material stacking area and all the temporary arrangement
should be removed.
5. No heavy scrap available at height.
6. During scrap hook cutting, it will be
ensured that the electrical cables are not damaged by cutting process. All
protection measures will be adopted to avoid any hazard at site.
SAFETY PRECAUTIONS:-
Ø
All
workmen will use the proper P.P.E. (Shoes, Helmet, Hand gloves, Safety Belt,
Goggles etc.
Ø
The
other safety requirements as per safety rule will be ensured.
Ø
The
proper work men will be deputed for the work.
Ø
Signal
will be given by fire watcher only.
Ø
Proper
barricading will be provided.
Ø
During
hot work fire fighting arrangement will be provided & spatter falling down
control measures will be taken.
EMERGENCY PROCEDURE:-
1. Site emergency vehicle
2. First aid arrangement.
3. Deployment of safety officer to deal
with emergency and rescue if required.
DEPLOYED STAFF TO PERFORM ABOVESAID
WORK:-
The
following staff member will execute and monitor the whole activity for assuring
the successful and safe completion of
all work in C.T.Riser Pipe U# 1 & 3 & 4
1.
Mr.
Ambica Patel :- Manager
2.
Mr.
Amit Ku. Chadi :-
Engineer
3.
Mr.
Mannu Tiwari :- Safety Officer
4.
Mr.
Jay Govind Choudhri :- Fitter.
MANPOWER /WORKERS
DEPLOYED FOR ABOVESED ACTIVITY:-
1
Ganges deployed (approximate 12 no. Workers):- C.T.Riser Pipe U# 1 & 3
& 4
PREPARED BY REVIEWED BY APPROVED
BY Mr. U. S. Seth
M/s SEPCO M/S BALCO (Tech. Advisor)
WORKER’S DETAILS
|
||||
S.N.
|
Name of persons
|
Designation
|
Pass No.
|
Signature
|
01
|
|
|
|
|
02
|
|
|
|
|
03
|
|
|
|
|
04
|
|
|
|
|
05
|
|
|
|
|
06
|
|
|
|
|
07
|
|
|
|
|
08
|
|
|
|
|
09
|
|
|
|
|
10
|
|
|
|
|
11
|
|
|
|
|
12
|
|
|
|
|
13
|
|
|
|
|
14
|
|
|
|
|
15
|
|
|
|
|
16
|
|
|
|
|
17
|
|
|
|
|
18
|
|
|
|
|
19
|
|
|
|
|
20
|
|
|
|
|
21
|
|
|
|
|
22
|
|
|
|
|
No comments:
Post a Comment